In May and June was held at Petrobras programmed shutdown P-37 unit production. To ensure compliance with the deadline for returning the platform production were done with plenty of organization.
The services requested were: Underwater general services at sea chests and overboard valve, helping to pull out and pull-in lines for gas-lift and production test of MSP-MRL-05 manifold as well as availability of specific procedures and suitably qualified personnel to carry out the review of the tasks. In the opinion of Dejaime Vasconcelos, sector manager at Petrobras P-37, Oceânica´s underwater intervention was extremely important. "The team worked where there was the need for corrective maintenance committed to safety and as scheduled, "he said.
To implement these services was requested by the unit's readiness from Oceanica´s team at a diverse schedule, including during the night. All the professionalism and performance of employees were recognized for the supervision of Petrobras with compliments on RDO's and ISC's.
According to the Oceanica’s technical of planning, Eric Richardson, this recognition is very important for the whole team involved in the work. "Many steps of the production breakdown depended on the solution of our services and the awareness of this need was absorbed by the entire team that has embraced this responsibility working with dedication and professionalism, "said Eric.
Congratulations to all!