Hydrostatic Test of GLP Pipelines
 |
In September, was completed with great success, the pre-commissioning of 8 "and 12" GLP pressurized pipelines between the Waterway Terminal Of Round Island in Guanabara Bay and the area of Terminal Champs Elysees (TECAM), Duque de Caxias, with our client Petrobras (Engineering \ IETEG \ IETR \ CMDSU).
The service performed encompassed the activities of filling, cleaning, calibration, with passage of Pigs, inspection with geometric pig and performing OF a hydrostatic test at 20 km of lines.
The implementation of these activities occurred between contract signing, manufacturing and approval of executive documentation, mobilizing and implementing activities in record time, according to the CMDSU records, which confirms the Oceânica position as a partner, focused on meeting the desires and needs of its customers with speed and quality required for this project. |
The next step is the accomplishment of the submarine pipeline hydrostatic test of the Submarine pipelines of water transportation and the network of fire fighting of the Terminal of Receiving of Liquefied Natural Gas of Guanabara Bay in order to conclude this project with CMDSU.
Also for 2011, there are plans to carry out pre-commissioning of the pipeline and PLEM Guamaré Waterway Terminal (TA GME), located in Rio Grande do Norte, in addition to the tests planned for 2012 of the lines of Ubarana, Paracuru and Atum Xaréu - CE lines also in Rio Grande do Norte.
For the Records It is to be congratulated all the engineering team and hydrostatic test of the Oceânica for the efforts and success in an enterprise and more completed |
 |
|
|
|
|